Shiqry Project by UKSOL Energy KSA: Pioneering Renewable Energy in Saudi Arabia
/Introduction
At UKSOL Energy KSA, we take pride in our role as pioneers in the renewable energy sector, particularly within the Kingdom of Saudi Arabia.
With the NEOM projects, we have made significant strides towards fulfilling the vision of a green and sustainable future for the region.
This article outlines our key projects and their impact on advancing renewable energy solutions in the Kingdom.
Project Overview
Our work within the NEOM initiative reflects our commitment to delivering high-quality, efficient, and sustainable energy solutions. Here’s a closer look at some of our standout projects:
NCV 3 - SATCO Camp (Executed in 2021)
In 2021, UKSOL Energy KSA executed a state-of-the-art hybrid plant for the SATCO Residential camp. The project components included:
4.5 MWp Solar Plant
7 x 1.825 MW Caterpillar Medium Voltage Generators
13.8 kV Switchgear Rooms with 13 SWGR Panels each
Hybrid Controller, AC-DC Panels, UPS
Two 1.6 MVAR Capacitor Banks
Diesel Network Tanks, Daily Tanks, Piping, and Automatic Filling Connections
This ambitious project was successfully commissioned in October 2024, marking a significant milestone in our renewable energy initiatives.
NCV 2 - Tamimi Camp (Executed in 2021)
Also in 2021, we completed the Tamimi Residential Camp Hybrid Plant, featuring:
5.5 MWp Solar Plant
Hybrid Controller interfaced with 26 Diesel Generators totaling 26 MW
This project was successfully commissioned in October 2021, showcasing our capability to integrate renewable energy with traditional power sources seamlessly.
NRC Projects (Executed in 2024)
In 2024, UKSOL Energy KSA completed several residential camp PV plants for Alfanar, each demonstrating our expertise in solar energy solutions. These projects include:
NRC 17-18 ALPH 3 Camp
5 MWp Solar Plant using half mono-facial and half bifacial PV modules
Fixed Structure with Two Different Heights to accommodate both types of modules
Commissioned in August 2024 within 45 days
NRC 19-20 ALPH 4 Camp
5 MWp Solar Plant with similar specifications to the ALPH 3 Camp
Commissioned in August 2024 within 45 days
NRC 11-12 ALPH 1 Camp
5 MWp Solar Plant following the same efficient design
Commissioned in August 2024 within 45 days
RC 13-14 ALPH 2 Camp
5 MWp Solar Plant with identical specifications and performance
Commissioned in August 2024 within 45 days
NRC 26 ALPH 5 Camp (Under Execution)
Currently, we are executing the Alfanar Residential Camp PV Plant for NRC 26 ALPH 5 Camp, which includes:
3 MWp Solar Plant with half mono-facial and half bifacial PV modules
Fixed Structure with Two Different Heights
This project began in August 2024 and is planned to be commissioned in the first week of October 2024.
Commitment to a Sustainable Future
Each of these projects underscores our unwavering commitment to advancing renewable energy solutions in Saudi Arabia.
By leveraging cutting-edge technology and expert curation, we are not only meeting but exceeding the expectations set forth by the NEOM vision for a greener future.
Conclusion
The successful execution of these projects is a testament to UKSOL Energy KSA's dedication to pioneering renewable energy in Saudi Arabia.
We invite business professionals and organisations to join us on this path towards a sustainable future.
Feel free to reach out to us for more information on our services and how we can help your organisation achieve its energy goals: https://uksolenergyksa.com/
Get in touch with UKSOL Energy KSA to learn more about our groundbreaking projects and how we can assist in your transition to renewable energy.
Together, let's pave the way for a greener tomorrow.